18 November 2026
Share Print

Getting deal-ready: The option agreement – Working in partnership with landowners

To The Point
(5 min read)

In the opening article in this series, we identified secure and transferable land rights as one of the first matters an investor will examine when assessing an energy project. This second article looks more closely at the agreement that establishes the land rights required for the project.

In the opening article in this series, we identified secure and transferable land rights as one of the first matters an investor will examine when assessing an energy project. This second article looks more closely at the agreement that establishes the land rights required for the project.

For a land-based energy project, the option agreement is the foundation for a relationship that continues through development, construction, operation and decommissioning. At the outset, it gives the developer time to establish whether the project is viable and to procure the necessary statutory consents  before committing to a long-term lease or purchase. During that period, the landowner agrees to make the land available for limited development activity and, subject to the agreed conditions, to enter into the long-term arrangement if the option is exercised.

Striking a balance matters. The developer needs sufficient control and flexibility to justify expenditure on planning, environmental assessment, grid and design. The landowner needs clarity on the land affected, the duration of the commitment, the payments to be made and the effect on the use and future ownership of the property and any adjoining land. If the agreement leaves either side uncertain on those points, difficulties may emerge at precisely the stage when the project is seeking investment or project finance.

Projects often require a combination of options to take a lease, options to purchase and options to acquire easements and rights of way. The following issues arise regularly across those agreements.

1. What land and rights does the project require?
2. Does the option period match the development programme?
3. What rights does the developer have?
4. What restrictions apply during the option period?
5. What consideration will the landowner receive, and when?
6. Can the project evolve without reopening the agreement?
7. Can the agreements move with the project and support finance?
8. Are the long-term terms genuinely agreed?
9. What happens if the project does not proceed?

A practical option agreement checklist

Before the option agreement is signed, the parties should be able to answer “yes” or identify a clear action plan for each of the following:

  • Parties and title: the owners, occupiers, mortgagees and other parties whose consent or participation is required have been identified;
  • Project footprint: the option area and anticipated project footprint, including potential access, cable routes, substations, compounds and other temporary and permanent rights, are mapped with sufficient flexibility for the footprint to be refined through the planning and development process;
  • Option period: the initial term, extension rights, notice requirements, payments (if any) and long-stop date reflect a realistic development programme;
  • Development activity: survey, investigation, access and application rights are clear, with workable protections for the land and farming or other operations;
  • Exclusivity: restrictions protect the proposed project without unnecessarily preventing the landowner’s continuing use of the property for the agreed purposes;
  • Payments: option, extension, exercise and long-term payments, indexation, costs and compensation are set out clearly;
  • Project changes: the agreement permits reasonable design and infrastructure changes and establishes when further consent or an adjustment to the commercial terms is required;
  • Transfer and finance: assignment, change of control, security, step-in and direct-agreement provisions can support investment, sale and project finance;
  • Long-term document: the lease, transfer or easement is attached in an agreed form and is consistent with the option and project maps;
  • Title protection: the appropriate method of protecting the option in the Registry of Deeds or Land Registry has been agreed, together with arrangements for releasing or cancelling any related registration when the option expires or is terminated; and
  • End of the option: expiry, termination, reinstatement, outstanding payments and the treatment of applications and project information are addressed.

Clear agreements support the project

Option agreements cannot remove the development risks inherent in an energy project. They can, however, provide the developer with a secure and workable basis on which to incur development expenditure and give the landowner a clear account of how the property may be used, for how long and on what financial terms.

That is what working in partnership requires in this context. The developer and landowner will not have identical interests, but each should understand the other’s role, protections and decision points. Regular communication during the option period remains important, particularly where the programme or design changes.

From an investment perspective, a coherent option and long-term land package demonstrates that the project controls its required footprint, can accommodate a realistic development programme and can be transferred and financed without reopening fundamental terms. Resolving those matters early protects the relationship and avoids delay when the project is ready to raise capital or proceed to sale.

The next conversation

Developers reviewing an existing option portfolio, or preparing to enter into new arrangements, may benefit from testing whether the land package remains aligned with the current project design, timetable and proposed funding route. A focused review can identify missing rights, consent or transfer issues and long-term terms that should be addressed before an investment or sale process begins.

Next in the series, Article 3: Beyond Planning Permission – Preparing an Energy Project for Investment?

Key contacts

Partner, Head of Energy & Infrastructure (Ireland)