Whilst the phrase “jointly and severally” is proliferate in many multi-party contracts, the decision of the Singapore High Court’s General Division’s decision in DRO v DRP [2025] SGHC 255 clarifies what it actually means alongside judicial guidance on pre-arbitral processes. Unincorporated joint ventures would do well to heed the lessons derived from this decision, which this month’s AG Insights explores.
Singapore High Court clarifies consortium member’s right to arbitrate and effect of pre-arbitration procedures
Introduction
The dispute in DRO v DRP [2025] SGHC 255 centred on a contract (the “Contract”) between the Owner (and Applicant in the case, DRO) and an unincorporated consortium consisting of an onshore partner (and Respondent in this case, DRP) as well as an off-shore partner (“Co A”).
The Contract provided that Co A and DRP shall “jointly and severally” be referred to as the ‘Contractor’ and that the Owner and the Contractor would be referred to as a ‘Party’ individually and ‘Parties’ collectively. This is not unusual.
The Respondent commenced an arbitration independently of Co A against the Applicant, claiming for payment for onshore works (the “Arbitration”). The Applicant filed but failed in a jurisdictional challenge in the Arbitration. The Applicant then applied to the Singapore High Court seeking, pursuant to section 10(3)(a) of the International Arbitration Act 1994, a declaration that the arbitral Tribunal lacked standing (or locus standi) to hear and determine the Arbitration on the basis that the Consortium had to jointly bring one. In the alternative, the Applicant requested that the Tribunal’s decision on jurisdiction be set aside on the ground that the pre-requisites to arbitration have not been met.
This month’s Insights article will focus on the ‘Standing Issue’ and the issue of whether pre-requisites to arbitration had been satisfied.
View all insights
INSIGHTS
9 September 2026
Singapore High Court rejects challenge to arbitral award on the merits disguised as a jurisdictional and procedural challenge
INSIGHTS
24 August 2026
Strategic use of SIAC rules in energy sector arbitrations
INSIGHTS
26 May 2026
Singapore High Court Clarifies Scope of Adjudication Review under SOPA
Key contacts
Partner, Construction & Engineering and Head of Korea Business Group
Singapore
To the Point
Subscribe to receive legal insights and industry updates directly into your inbox
Sign up nowGet up to date with our latest news on LinkedIn
Follow now