Ireland is looking to show the global data centre industry that it is open for new business through a series of recent policy and regulatory shifts. Data centre developers and investors need to understand these new requirements when securing a new electricity grid connection from EirGrid plc, particularly the requirements for on-site or nearby dispatchable generation and sourcing at least 80% of energy from new renewable sources within six years. While these changes are welcome, ongoing judicial review proceedings create uncertainty. Developers and investors should therefore take caution that grid connection policy may change depending on the outcome of the proceedings.
New policy direction for data centre developers in Ireland
Key Policy Developments
While Ireland, specifically Dublin, established itself as an internationally recognised data centre hub through a decade long period of rapid data centre development, this development effectively came to a halt in 2021. At that time, Ireland’s energy regulator, the Commission for Regulation of Utilities (CRU), implemented strict criteria for new data centres seeking to connect to an under-strain grid, against a backdrop of limited parallel investment in upgrading the national electricity grid.
Recent policy developments signal that at an official level Ireland is ready to re-start its data centre industry. The most noteworthy development is the CRU’s Decision on Large Energy Users connection policy published in December 2025 (the LEU Policy). This was followed by the publication by the Irish Government of the Large Energy User Action Plan (LEAP) in January 2026, which contains 17 actions intended to facilitate future investment in energy-intensive sectors while unlocking Ireland’s renewable energy potential.
The LEU Policy has, in turn, led to an updated ‘Data Centre Connection Offer Process and Policy’ (DCCOPP) from EirGrid plc (the operator of the transmission grid in Ireland), published on 20 May 2026. The updated DCCOPP transposes the requirements set out in the LEU Policy, which will have a significant impact on the data centre industry in Ireland.
CRU LEU Policy
As noted above, the key policy development has been the publication of the LEU Policy by the CRU in December 2025, which indicates a shift in the approach of Ireland’s energy regulator from its 2021 position in how large energy users will be treated from a policy perspective. This policy change has not gone unnoticed and the LEU Policy is currently the subject of an active judicial review challenge, with the proceedings ongoing at the time of writing.
The LEU Policy seeks to provide a way forward for data centre developers that require access to the electricity grid, while at same time addressing both grid security and climate emission concerns. In this regard, two main pillars of the LEU Policy are:
- a requirement on an applicant to install an autoproducer unit or dispatchable on-site generation and / or storage (depending on the size of the data centre) and sell electricity back to the grid. This effectively represents a new business line for data centre developers; and
- a requirement on an applicant to procure a minimum of 80% of its energy from renewable sources, with a six-year glide path from the data centre’s energisation date to achieving this. This will likely be achieved through entering into a long-term corporate power purchase agreement (CPPA) with a renewable energy developer.
Under the LEU Policy, an important consideration for the system operators in determining whether to grant a connection is if a data centre is proposing to locate in a constrained or unconstrained area of the electricity network. This is particularly relevant for the Greater Dublin Area, which, unsurprisingly, has been designated as a constrained area by the CRU.
DCCOPP
The DCCOPP applies to all new data centre connection applications to the transmission system that are greater than 1 Mega-Volt-Ampere (MVA), which are made on or after the date of the LEU Policy decision on 12 December 2025. It replaces previous versions of the DCCOPP for these applications.
The revised DCCOPP applies different criteria depending on the size of the data centre. In summary:
View our table summarising the sizing criteria here.
From an industry perspective, most data centres are likely to have an MIC greater than 10 MVA, and the requirements set out in the table below will apply.
View our table of the requirements here.
The time required to process an application under DCCOPP will depend on what stage the associated generation is at. Where the associated generation has gone through the ECP-GSS process, a 7.5-month timeline from application receipt to issuance of a connection offer applies. However, for data centre applications whose associated generation has only just applied into ECP-GSS, an 18-month processing timeline applies.
It is important to note that in light of the LEU Policy being subject to current judicial review proceedings, applicants under DCCOPP are being put on notice by EirGrid that grid connection policy may be subject to change depending on the outcome of the proceedings.
Conclusion
While LEU Policy / DCCOPP has set a clear pathway for data centre development in Ireland, it remains to be seen whether it will have the desired effect of re-starting the industry, albeit in a sustainable way that maintains security of supply and incentives renewable development. This may not become clear until the judicial review proceedings are resolved, as many developers will, understandably, be reluctant to proceed with their projects until these proceedings are settled and there is certainty on the application criteria.
Beyond recent policy developments, the Irish Government envisages data centre policy changing to a ‘plan-led’ approach. This transition is set out in the LEAP, which places particular emphasis on renewable energy providing the primary power source in this approach. The CRU has recognised that the medium to long-term development of the data centre sector requires a plan-led approach encompassing spatial planning, development targets and plan-led infrastructure development. This would represent a shift from a developer-led approach towards something closer to a national infrastructure strategy, which is a shift in approach that has taken place in the Irish offshore wind sector in recent years.
The recent policy developments have been positive in demonstrating a desire at official level in Ireland to facilitate further data centre development. However, greater certainty around the application of the LEU Policy and the broader strategic direction for industry development would be beneficial for developers looking to participate in the development of the industry in Ireland once again.
Next steps
If you have a query that you would like to discuss, please get in touch with one of our specialists.
Related insights
Key contacts
Partner, Head of Energy & Infrastructure (Ireland)