On 18 November 2025, the Qatari Court of Cassation (Civil Chamber) delivered a landmark judgment in Cassation Appeal No. 1075/2025, arising from a complex, multi-party dispute over one of the mega construction projects in Qatar. The decision provides authoritative guidance on the treatment of concurrent delay, the enforceability and scope of pay-when-paid clauses, and the prohibition of double compensation in construction contracts.
Qatari Court of Cassation clarifies key principles in major construction dispute: Concurrent delay, pay-when-paid clauses, and double compensation
Background
The dispute originated from a subcontract executed in 2011 for works on a major Qatari construction project. Two subcontractors brought proceedings against the main contractors, seeking substantial unpaid sums, compensation for project delays, and the return of a QR 43 million performance bond. The main contractors resisted these claims, arguing that delays were concurrent and that their payment obligations were conditional upon receipt of payment from the project owner, relying on so-called "back-to-back" or "pay-when-paid" provisions.
The litigation was protracted, involving consolidated claims, expert reports, and multiple court decisions. Ultimately, the Court of Appeal awarded the subcontractors over QAR 142 million, including compensation for delay and sums related to bank guarantees. The main contractors appealed to the Court of Cassation.
Key legal principles clarified
The Court's decision
The Court of Cassation:
- Partially overturned the appellate judgment in respect of the duplicated compensation award;
- Rejected the claim for the additional QAR 4 million in damages;
- Upheld all other findings, including liability for delay, entitlement to subcontractor payments, and the interpretation and scope of pay-when-paid provisions, particularly as they relate to prolongation costs;
- Ordered costs accordingly.
Significance for the construction industry
This judgment provides important clarification for parties involved in construction projects in Qatar, particularly regarding the allocation of risk for delay and the enforceability of pay -when-paid clauses. The Court's distinction between payment for executed works and compensation for prolongation costs under pay-when-paid clauses is especially noteworthy, marking a significant development in Qatari construction law.
Related insights
INSIGHTS
1 April 2026
Strict procedural compliance and the ‘Pay Now, Argue Later’ principle under the Building and Construction Industry Security of Payment Act
INSIGHTS
26 February 2026
Time to ‘examine’ your right to terminate for insolvency under a construction contract?
INSIGHTS
9 February 2026
Singapore High Court clarifies consortium member’s right to arbitrate and effect of pre-arbitration procedures
Key contacts
Related specialisms
Related locations
To the Point 
Subscribe to receive legal insights and industry updates directly into your inbox
Sign up now