21 April 2026
Share Print

Qatari Court of Cassation clarifies key principles in major construction dispute: Concurrent delay, pay-when-paid clauses, and double compensation

To The Point
(3 min read)

On 18 November 2025, the Qatari Court of Cassation (Civil Chamber) delivered a landmark judgment in Cassation Appeal No. 1075/2025, arising from a complex, multi-party dispute over one of the mega construction projects in Qatar. The decision provides authoritative guidance on the treatment of concurrent delay, the enforceability and scope of pay-when-paid clauses, and the prohibition of double compensation in construction contracts.

Background

The dispute originated from a subcontract executed in 2011 for works on a major Qatari construction project. Two subcontractors brought proceedings against the main contractors, seeking substantial unpaid sums, compensation for project delays, and the return of a QR 43 million performance bond. The main contractors resisted these claims, arguing that delays were concurrent and that their payment obligations were conditional upon receipt of payment from the project owner, relying on so-called "back-to-back" or "pay-when-paid" provisions.

The litigation was protracted, involving consolidated claims, expert reports, and multiple court decisions. Ultimately, the Court of Appeal awarded the subcontractors over QAR 142 million, including compensation for delay and sums related to bank guarantees. The main contractors appealed to the Court of Cassation.

Key legal principles clarified 

1 Concurrent delay and apportionment of liability
2 Pay-when-paid clauses: Clarification on prolongation costs
3 Defects and acceptance of works
4 Prohibition of double compensation

The Court's decision 

The Court of Cassation:

  • Partially overturned the appellate judgment in respect of the duplicated compensation award; 
  • Rejected the claim for the additional QAR 4 million in damages; 
  • Upheld all other findings, including liability for delay, entitlement to subcontractor payments, and the interpretation and scope of pay-when-paid provisions, particularly as they relate to prolongation costs; 
  • Ordered costs accordingly. 

Significance for the construction industry 

This judgment provides important clarification for parties involved in construction projects in Qatar, particularly regarding the allocation of risk for delay and the enforceability of pay -when-paid clauses. The Court's distinction between payment for executed works and compensation for prolongation costs under pay-when-paid clauses is especially noteworthy, marking a significant development in Qatari construction law.

To the Point 


Subscribe to receive legal insights and industry updates directly into your inbox

Sign up now