Energy infrastructure optimisation case studyHow some high voltage thinking saved our client over £100m

Energy infrastructure optimisation case studyHow some high voltage thinking saved our client over £100m

Another client success story, supported by Addleshaw Goddard.

When one of the world’s leading automotive companies purchased a large plot for a major new factory, on paper everything looked perfect. There was ample space for a state-of-the-art facility, a test track and all they’d need to attract leading global talent. Except for one problem: there wasn’t enough power to support their ambitious future growth plans.

We were approached to explore what energy infrastructure work they could undertake to create sufficient power, from wind and solar farms to waste-to energy plants. Then a simple question led to a surprisingly straightforward solution and over £100 million saving.

Share Print

A few fast facts

£100m +

10

10,000

One

saving

Years

Volts

Relieved CEO





Over £100 million saving from connecting to the transmission network.

10 years of sequencing and stress cut down to less than 12 months.

10,000 volts of energy available with a signature and a spur line.

One relieved (and very happy) CEO.

£100m +

10

saving

Years



Over £100 million saving from connecting to the transmission network.

10 years of sequencing and stress cut down to less than 12 months.

10,000

One

Volts

Relieved CEO



10,000 volts of energy available with a signature and a spur line.

One relieved (and very happy) CEO.

The challenge


Once development work began and it became clear that the site was ideally suited for even more expansion, it also became clear that there wasn’t sufficient power on the electricity distribution network to support that additional expansion.

Thoughts turned to re-enforcing the network through local power generation,  for example, building multiple different sustainable power plants, and we were asked to prepare a report on the options. Building that many generation plants would be expensive and operationally challenging.

But seemingly the only alternative to connecting to the distribution network came with an eyewatering £120 million price tag.

challenge board outline

The solution


Facing a crippling capital outlay, we came up with a far more cost-effective option: connect directly into the main transmission network. This is the more powerful line that typically moves electricity from power plants to substations, rather than the Distribution line which moves electricity from substations to consumers.

And, because the transmission network was close to the site and because of the client’s large demand, it was an eminently viable option. Our client talked to the operator of the transmission network at National Grid and soon had an offer to connect to the transmission network, with a cost of just £10 million. Over £100 million less than feared.

lightbulb icon outline

The impact


With no need for a major sustainable energy infrastructure programme spanning nearly a decade and at a fraction of the potential cost, our client was able to power ahead with their development. No delays. No complex scheduling. And very few limitations in terms of what they could do.

What’s more, they now had a dependable supply of power direct from the grid but still the option of going more “green” over time. With some imaginative thinking, we helped save 8+ years of management hassles and a decade of development headaches.

Impact - targets

High Voltage case study


How some high voltage thinking saved our client over £100 million

Download the PDF  

Related expertise