On 16 April 2025, Circular 2/2025, of 9 April, of the Spanish National Markets and Competition Commission ("CNMC"), was published in the Official State Gazette (the "Circular"). This Circular establishes the methodology and conditions for access and capacity allocation in the natural gas system. The Circular will come into effect on 1 July 2025 and repeals Circular 8/2019 [1]. This Newsletter analyses the application of the Circular from the perspective of the connection and access of production plants of other gases [2] different to natural gas, focusing on renewable gases (such as hydrogen or biomethane).
Introduction and context
The scarce existing regulation regarding the connection of renewable gas production plants can be found in RDL 14/20223 [3], which added Article 12 bis to Royal Decree 1434/2002 [4], under the heading connection of renewable gas production plants to transport or distribution grids. This Article, which establishes very general provisions, delegates to the CNMC the approval of a specific procedure for managing connections of renewable gas generation plants.
The Circular aims at two main objectives. On the one hand, to review access mechanisms to gas infrastructures and introduce anti-hoarding measures applicable to renewable gas production plants. On the other hand, to update and adapt connection, access, and capacity allocation conditions to the new needs arising from decarbonisation and the promotion of renewable and low-carbon gases.
Thus, the Circular aims to: (i) establish general principles and rules for connection and access procedures for gases that can be injected into the grid without mixing (such as biomethane) and those requiring mixing (such as hydrogen); (ii) establish transparency and publicity requirements for transport and distribution grid operators regarding (among other things) available capacity in their grids; and (iii) specify congestion management and anti-hoarding mechanisms applicable to the production plants of such gases.
Based on Article 12 bis of Royal Decree 1434/2002 and prior to the approval of the Circular, the CNMC approved its Resolution of 19 April 2024, which established the management procedure for connections of biomethane generation plants to the transport or distribution grids (the "Resolution of 19 April 2024"). In this sense, to this date the CNMC has not approved specific procedures applicable to other renewable gases, such as hydrogen.
Regarding the Resolution of 19 April 2024, the CNMC is processing a new resolution to replace it, aiming to establish a procedure for managing requests and procuring connections for production plants of other gases in general (whether they require mixing or not, renewable or otherwise), in line with the Circular. According to its Justification Report (Memoria Justificativa) [5], this is expected to come into effect on 1 July 2025.
Although the Circular provides a necessary regulatory framework to ensure legal certainty in the connection and access of renewable gas production plants to the gas system, some key aspects for producers of these gases remain to be developed. As the injection of such gases into the gas system increases, it is likely that this regulatory framework will need to be revised to adapt it to the sector's new needs.