The most recent case, Wiener Wohnen [4], follows an earlier Italian case, Pizzarotti [5]. Let's look briefly at each.
In Pizzarotti, a new court complex was to be built in Bari. The origins of the case were odd, and involved the winning bidder in a process arguing that the Italian authorities should follow through on the award of a contract to it. A defence raised was that the process leading to the award to Pizzarotti was unlawful as it amounted to the award of a works contract, in contravention of procurement law. That issue was submitted to the European Court for a decision.
Relying on previous case law, the court said that where a contract contained elements which could be differently categorised (in this case, works and a land deal) it was necessary to look at the main object of the contract.
Crucially, the court held that, where (as in this case) the building concerned had yet to be built, the main object would generally be works.
But it noted that there is another requirement if an agreement is to constitute a public works contract for the purposes of the rules: that (in the words of the court's judgment) the authority "has taken measures to define the characteristics of the work or, at the very least, has had a decisive influence on its design."
In the Pizzarotti case, the court decided that the requirements laid down by the Italian authorities put them in the position of decisive influence so that the transaction was properly to be viewed as a public works contract subject to the Italian procurement rules. So Italy 0.
But the second half has delivered a late victory for authorities and developers and suggested a game plan which can be used by teams in the future.
Wiener Wohnen ("WW") is a large public body based in Vienna and responsible for public housing. It needed new office space and engaged a consultant to find suitable locations. Those identified included a site on the Guglgasse on which a developer, Vectigal, proposed to build offices.
The proposed building consisted of two blocks, imaginatively named A and B, with the possibility of bridges to connect them. WW took an indefinite duration lease from Vectigal with a break at 15 years and at 10-year intervals thereafter. It also took options on 3 additional floors, which options were later exercised.
The European Commission attacked the transaction, alleging it amounted to a public works contract. Specifically, citing Pizzarotti, it pointed to:
- the decision in that case to the effect that the main object, where a building was yet to be constructed, was generally to be considered to be the execution of works rather than merely a land deal;
- the optional bridges between blocks A and B, the construction of which it alleged WW had influenced;
- the additional floors which WW could (and indeed did) call off;
- a series of requirements laid down by WW in specifications which were attached to the lease, and which it alleged gave it decisive influence over the construction of blocks A and B, going beyond what would be expected if WW were merely stipulating those matters which would be expected to be of concern to a 'mere' tenant; and
- the fact that WW appointed a consultant to oversee the construction works.
The Commission alleged that, without WW's involvement, blocks A and B would not have been built. It also alleged that the building was not simply a standard building, further pointing to WW's decisive influence.
The Austrian government defended the Commission's action on the basis that the procurement rules did not apply because of the land exemption. There was also much discussion of the extent to which WW's specifications merely encapsulated existing legal requirements on environmental and other matters. Austria argued that these requirements didn't go beyond the remit of a potential tenant.
The court found in Austria's favour and threw out the Commission's action. Although, echoing Pizzarotti, it said that the immediate object of the contract was the construction of the two blocks, it emphasised the need for WW to have "taken measures to define the characteristics of the [blocks] or at the very least to ha[ve] had a decisive influence on its design" if the deal was to be considered a public works contract and subject to the rules. That would be the case if WW's requirements had gone beyond the usual requirements of a tenant, but was not the case here.
In a little more detail:
- the amount paid and payment arrangements may be relevant but will not in themselves constitute decisive influence;
- the presence or absence of a repurchase option or options to let additional space is irrelevant, as is lease duration;
- the court further defined "decisive influence" as being constituted by influence over architectural structure such as the building's size, external walls and loadbearing walls. In contrast, it said:
- stipulations concerning interior fittings demonstrate decisive influence only if they are distinguished because of their specificity or scale; and
- laying down specifications to ensure that the building complied with the normal ‘state of the art’ on the market concerned were normal concerns of a tenant and therefore non-problematic;
- the mere fact that there were a large number of detailed stipulations from WW was not, in itself problematic if they passed the test of being tenant-like requirements; as an example, a stipulation as to the size of the buildings' electrical supply was a legitimate tenant concern;
- the court found that planning for the building had been completed when WW had identified the Guglgasse site as a possible location, and that the additional floors and bridges were not planned in order to meet a specific requirement of WW;
- in contrast, the court said, it is normal for a tenant "…which seeks to rent an office building to make its wishes clear as to the specifications which that site should, as far as possible, meet whether in respect of a building which is yet to be constructed or a change of tenant where upgrade work is carried out. Such steps do not allow a lease to be reclassified as a works contract."