The court has handed down its decision in a landmark rights of light case concerning the Bankside Yards development. In this article, we focus on how the court exercised its discretion as to whether to grant the Claimants an injunction and, having decided that damages were an adequate remedy, how those damages were assessed. We also consider the implications of the judgment for developers and the potential impact on the rights of light insurance market.
Rights of light – what developers need to know about the Bankside Yards case
Background
The High Court’s judgment in Cooper v Ludgate House Limited is a landmark decision on rights of light. Whilst it contains only limited new law, it is rare for such a case to get to trial and it provides helpful guidance to developers on how the court will exercise its discretion on whether to grant an injunction and, if not, how to assess damages. Developers will take comfort from the fact that the court did not grant an injunction.
The Court’s discretion on whether to grant an injunction
The court's decision to refuse to grant an injunction was based on a careful balancing exercise weighing the harm to the Claimants against the harm to the developer’s legitimate interests and the public benefit in retaining the already constructed development.
Developers should however note that Mr Justice Fancourt was clear that arguments of waste of money and harm, which could be made by developers in any case where an injunction is sought to demolish an already built building, are not an automatic defence to the grant of an injunction. They will not trump “wrongful conduct that causes serious harm” and developers who seek to cynically rely upon this judgment without being open about what they intend to build are “unlikely to receive much sympathy from the court”. The developer in this case avoided an injunction in part as the court found that they did not act “unfairly, exploitatively or covertly” by adopting a commercial strategy to rights of light issues.
Developers should not interpret this judgment as a licence to proceed with impunity.
How damages were assessed
The developer argued that damages should be calculated on the basis of the diminution in value of the Claimants’ properties. The court rejected this argument and said that, if this was the correct measure of damages, it would be inadequate to compensate the Claimants and, if the developer had been correct on this point, it would have been a strong argument in favour of granting injunctive relief on the basis that damages would not be an adequate remedy.
The court instead determined that damages should be assessed on the basis of a hypothetical negotiation between a willing seller and a willing buyer as at August 2019 (the date was agreed between the parties, being the date just before construction began). Settlements agreed with other adjoining owners were informative, but not direct evidence of what would have been agreed in this hypothetical negotiation. The court also clarified that the negotiations are not a ransom exercise. Instead, the parties know that the Claimants could apply for an injunction and might obtain one, but, on the other hand, the parties know that the developer has the ability to seek a resolution under section 203 of the Town and Country Planning Act 2016 (Section 203) to remove the injunction risk.
The court determined that the parties would have agreed in this hypothetical negotiation that the developer would pay 12.5% of its perceived gain to a compensation pot. This is lower than the figure of 1/3rd often quoted as a starting point in negotiations (based on previous cases). This gave a pot of £3.75 million to be split between all adjoining properties impacted by the development (not just the Claimants). The court then assessed that, of this pot, £1.25 million would be allocated to the Claimants, which resulted in a figure of £725,000 for the Powells and £525,000 for Mr Cooper.
In accordance with previous authorities, the court then stood back and considered whether the sums felt right. The court determined that they were high when compared to the value of the Claimants’ properties. It therefore awarded damages of £500,000 for the Powells and £350,000 for Mr Cooper. These were substantial when compared to the value of the Claimants' properties (£900,000 to £950,000 for the Powells and £1.05 million to £1.1 million for Mr Cooper), the original offers made to them by the developer (£36,000 and £23,000 respectively) and the court’s view of the diminution in value of their properties (£60,000 and £20,000 respectively), but significantly lower than the sums claimed by the Claimants at trial (not less than £3 million and £3.37 million respectively).
Waldram v Radiance and Section 203
For professionals involved in rights of light work, there were other very helpful comments made in the judgment including on how to assess right of light impacts. We would be very happy to discuss these technical aspects further.
Implications for developers
This decision provides reassurance to developers that courts will undertake a careful balancing exercise and are willing to refuse to grant injunctions in favour of damages. However, developers should not interpret this judgment as a licence to proceed with impunity. Each case will be decided on its own facts and the court’s decision was influenced by the developer’s conduct and the significant public benefits of the development. Developers should:
- obtain professional advice on rights of light issues as early as possible to navigate this complex area of law;
- carefully consider their conduct, including which adjoining owners they need to engage with and when to start such engagement;
- consider the potential role of Section 203 in unlocking developments.
Implication for rights of light insurance
It is possible that, whilst the Claimants did not get an injunction, adjoining owners and those that act for them might be emboldened by the damages awarded to the Claimants and seek higher sums than they have previously. This in turn might have an impact on terms that rights of light insurers are willing to provide, including potentially increasing deductibles in such policies. Watch this space.
Related insights
Insights
A roadmap to zero-emission buildings: European Commission releases 2025 EPBD Guidance

Insights
Nationwide RPZ Expansion Brings New Rent Control Obligations

Insights
Build or face consequences: Government's bold proposals to accelerate housing delivery – technical consultation

Key contact

Related Sectors
Related Specialisms
To the Point 
Subscribe for legal insights, industry updates, events and webinars to your inbox
Sign up nowGet up to date with our latest news on LinkedIn
Follow now